The US 19 PD&E Re-evaluation Study began in February 2016. The project activities included collecting information, developing roadway improvement alternatives and evaluating the potential environmental and social effects of the “no-build” and “build” alternatives.
A public hearing was held on October 30, 2018 and the study was completed on October 30, 2019.
PD&E Study Schedule | |
Data Collection & Traffic Analysis | Spring 2016 |
Develop & Evaluate Alternatives | Summer 2016 |
Prepare Draft Reports | Summer/Fall 2018 |
Hold Public Hearing | October 30, 2018 |
Prepare Final Reports | Winter/Spring 2019 |
Final OEM Approval | October 30, 2019 |
FDOT Tentative 5-Year Work Program | ||
Fiscal Year 2019/2020 through Fiscal Year 2023/2024 | ||
Project Phase | Short Term Improvements | Full Improvements |
Design | FY 2019 | Not Currently Funded |
Right-Of-Way | FY 2023 | Advanced Aquisition to begin FY 2023 |
Construction | Not Currently Funded | Not Currently Funded |